Resources - Norm Time Setup
Norm Time Codes are created on the Norm Time List page. Each Resource has a Time Configuration Code which contains a Norm Time Code, on the Resource Card > Timesheet FastTab, and defines the expected time entry setup. For more information on Timesheet Configuration Setup, see: Using Timesheet Configuration List
Norm Time is the basis for creating capacity for the resource. The Update Capacity feature generates maximum availability for a resource based on their normal working schedule (Norm Time). Norm Time is generally related to the time period for the resource. If the resource has a time period of 40 hours weekly, over 5 days, then the Norm Time Code used could be 40-5 and Update Capacity will assign normal working hours of 8 hours each day for the resource. For more information on setting capacity for a resource, see: Set Capacity for a Resource
Create new Norm Time Codes
Navigate to the Role Center > Setup > Resource Setup > Norm Time
Code: Create a code for the Norm Time. Examples: MO, WK, SMO, BI WK.
Description: Enter the Description for this Norm Time. Examples: Monthly, Weekly, Semi-monthly, Bi-weekly.
Tip
To access Timesheet Configuration for a specific resource, navigate to the Role Center > Resources > Resources > More Options > Actions > Time Setup > Timesheet Configuration.